October 18 – Leonard Lawrence Elementary

Work is continuing on replacement of the existing roof systems at Leonard Lawrence Elementary. Approximately 95% of the shingle replacement has been completed and approximately 50% completed on the flat roof areas. Installation of the wall panels of the clerestory walls will be starting the week of 10/23/17. It is anticipated that the installation of the roofing systems will be completed by the end of October.

 

October 18 – Bellevue East

HVAC PROJECT
Advanced Engineering Systems (AES) presented preliminary plans and recommendations at the Bellevue School Board meeting on October 9th for the planned HVAC renovation and upgrade at Bellevue East. After analysis of the building, AES made a recommendation to install a variable refrigerant flow (VRF) system in the existing building to replace the existing steam boiler heating and central chiller unit cooling systems currently found within the building. Their recommendation was proposed after reviewing five different HVAC options for the building which took into consideration initial cost, annual maintenance costs, energy efficiency, constructability capabilities while trying to keep the existing school operational, as well as overall life cycle costing based on a 50 year operation. Based on these factors, the proposed VRF system scored the best overall which resulted in the recommendation. Anticipated construction costs for the project will likely exceed what has been initially budgeted for the project, but savings on other projects as well as a higher premium in proceeds from the sale of last round of bond purchases does provide additional dollars that can be applied for the project. The Board voted to direct AES to proceed with the continuation of the design and to move forward to prepare construction bid documents for the proposed work. It is anticipated that the project will be sent out to prospective bidders in late January or early February in hopes of starting construction in late Spring of 2018.

October 18 – Bellevue West

Roof Projects
The roofing work for the first round of roof replacement work scheduled for Bellevue West is moving forward. Work is ongoing in Area 1 (Northwest quadrant) and the work in that area and will be moving over to Area 2 (Language Classrooms). Work on the north portion of the building will be completed the week of 10/23/17 and then will shift over to the south end of the building to the shop classroom area and the roof area over the pool. Roofing work is anticipated on being completed in early November.

A contract has also been awarded to Controlled Comfort, Inc. on extending six existing rooftop unit curbs in the areas of work to allow flashing work to be performed on the roof curbs. This work will be coordinated with the installation of the roofing work that will be performed in these respective roof areas.

 

July 31st, 2017 – LeMay Elementary

The planned work at LeMay Elementary for the life safety and HVAC renovation work is wrapping up this week with the installation of the classroom heating/cooling units in the west wing of the building. The new chiller unit installed at the building is scheduled to go on-line on August 1st with all finish work revolving around the mechanical installation being wrapped up by August 4th. The new fire sprinkler, intercom and wireless technology upgrade work is also nearly complete and will also be fully operational by the start of school on August 10th.

   