February 21, 2019 – Mission Middle School
As part of the bond work scheduled in the District, one of the items scheduled for replacement place the existing bleachers in the gym at Mission Middle High School. The new seating will replace the existing wood bleachers with new retractable contoured plastic bench seats. Work on the installation of the new bleachers were completed just prior to the end of the year and are in full use.
The Bellevue School District is looking at completing renovations to the existing track at Mission. The track at the school was omitted from the initial proposed bond work, but in review of existing conditions, it was determined that the condition of the track was actually in worse condition than the other middle school tracks in the District. Engineering plans are currently being prepared to replace the existing asphalt track with a new asphalt track with miscellaneous revisions around the track. Bids will be received in mid-March for consideration by the Board in April 2019.