July 31st, 2017 – Leonard Lawrence
The Contract for the roof replacement work at Leonard Lawrence was awarded to 10 Men Roofing and they have been moving hard on the first phases of the roof project. The Contractor has been tackling the removal of most of the roofing on the shingled portion of the project and is anticipating having a majority of the new shingled roof areas completed by August 10th, which is critical since most of the classrooms are located under the shingled areas. Materials for the replacement of the flat roof areas should be arriving on-site the first week of September to allow for start of the work on the flat roof areas. Work on all of the roof areas is scheduled to be completed by the end of October.