July 31st, 2017 – LeMay Elementary
The planned work at LeMay Elementary for the life safety and HVAC renovation work is wrapping up this week with the installation of the classroom heating/cooling units in the west wing of the building. The new chiller unit installed at the building is scheduled to go on-line on August 1st with all finish work revolving around the mechanical installation being wrapped up by August 4th. The new fire sprinkler, intercom and wireless technology upgrade work is also nearly complete and will also be fully operational by the start of school on August 10th.